Permit processing times in ZIP 60608
Across 4,677 issued permits assigned to ZIP 60608, the median processing time was 2 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Permit processing times in ZIP 60608, 4,677 issued permit records show a median processing time of 2 days; 75% were issued within 26 days and 90% within 110 days, covering January 2021 through September 15, 2026.
The median was 1 day slower than the previous 12 months.
Permit processing times in ZIP 60608: wait distribution
For Permit processing times in ZIP 60608, 4,677 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Permit processing times in ZIP 60608: annual permit timing
Permit processing times in ZIP 60608 has 6 publishable issue-year cohorts spanning 2021–2026, representing 4,677 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 893 | 0 days | 9 days | 76 days |
| 2022 | 949 | 0 days | 10 days | 98 days |
| 2023 | 781 | 0 days | 13 days | 106 days |
| 2024 | 849 | 8 days | 40 days | 120 days |
| 2025 | 713 | 7 days | 42 days | 119 days |
| 2026* | 492 | 10 days | 45 days | 113 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Permit processing times in ZIP 60608: ZIP codes with similar overall timing
Permit processing times in ZIP 60608 has 4,677 issued records, a 2 days median, and a 26 days 75th-percentile wait in this release.
More Permit processing times in ZIP 60608 comparisons
The Permit processing times in ZIP 60608 cohort contains 4,677 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 1 dayRenovation & Alteration 42 daysEasy Permit Process 0 daysSigns 22 daysNew Construction 56 daysElevator Equipment 0 daysWrecking & Demolition 0 daysReinstated Permit 0 days