Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP boundary report

Permit processing times in ZIP 60608

Across 4,677 issued permits assigned to ZIP 60608, the median processing time was 2 days.

Records checked4,6772021–Sep. 15, 2026

The short answer

Typical wait2 daysmedian issued permit
Usually within26 days75% of records
Long-wait edge110 days90% of records
Evidence4,677issued permits

The median was 1 day slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
42.1%
1–7 days
19.5%
8–30 days
15.0%
31–90 days
11.4%
91+ days
12.0%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20218930 days9 days76 days
20229490 days10 days98 days
20237810 days13 days106 days
20248498 days40 days120 days
20257137 days42 days119 days
2026*49210 days45 days113 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

ZIP codes with similar overall timing

ReportMedian75% withinRecords
606062 days15 days6,775
606082 days26 days4,677
606132 days21 days2,994
606162 days25 days2,939
606182 days27 days6,576
606212 days23 days2,516
606232 days24 days4,182
606242 days21 days2,944