Renovation & Alteration permits in ZIP 60632
The median renovation & alteration permit wait in ZIP 60632 was 49 days, based on 485 issued records.
Records checked4852021–Sep. 15, 2026
The short answer
Typical wait49 daysmedian issued permit
Usually within112 days75% of records
Long-wait edge229 days90% of records
Evidence485issued permits
The median was 22 days slower than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 87 | 1 day | 47 days | 118 days |
| 2022 | 97 | 8 days | 75 days | 141 days |
| 2023 | 88 | 49 days | 115 days | 250 days |
| 2024 | 83 | 63 days | 172 days | 268 days |
| 2025 | 80 | 96 days | 133 days | 210 days |
| 2026* | 50 | 88 days | 120 days | 338 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context