Renovation & Alteration permits in ZIP 60623

The median renovation & alteration permit wait in ZIP 60623 was 44 days, based on 972 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked9722021–Sep. 15, 2026

The short answer

For Renovation & Alteration permits in ZIP 60623, 972 issued permit records show a median processing time of 44 days; 75% were issued within 107 days and 90% within 216 days, covering January 2021 through September 15, 2026.

Typical wait44 daysmedian issued permit
Usually within107 days75% of records
Long-wait edge216 days90% of records
Evidence972issued permits

The median was 25 days slower than the previous 12 months.

Renovation & Alteration permits in ZIP 60623: wait distribution

For Renovation & Alteration permits in ZIP 60623, 972 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
17.6%
1–7 days
12.1%
8–30 days
12.8%
31–90 days
27.0%
91+ days
30.6%

Change over time

Renovation & Alteration permits in ZIP 60623: annual permit timing

Renovation & Alteration permits in ZIP 60623 has 6 publishable issue-year cohorts spanning 2021–2026, representing 972 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20212066 days71 days146 days
20222035 days65 days147 days
202314841 days111 days196 days
202417062 days115 days210 days
202514369 days161 days271 days
2026*10294 days178 days266 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration permits in ZIP 60623: Renovation & Alteration timing in comparable ZIP codes

Renovation & Alteration permits in ZIP 60623 has 972 issued records, a 44 days median, and a 107 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 6062344 days107 days972
ZIP 6063443 days109 days457
ZIP 6063645 days112 days596
ZIP 6064343 days108 days556
ZIP 6070743 days106 days152
ZIP 6060842 days115 days1,029
ZIP 6062242 days100 days1,099
ZIP 6065542 days85 days250