Renovation & Alteration permits in ZIP 60707
The median renovation & alteration permit wait in ZIP 60707 was 43 days, based on 152 issued records.
Records checked1522021–Sep. 15, 2026
The short answer
Typical wait43 daysmedian issued permit
Usually within106 days75% of records
Long-wait edge181 days90% of records
Evidence152issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 35 | 34 days | 72 days | 168 days |
| 2022 | 32 | 37 days | 81 days | 197 days |
| 2023 | 18 | 50 days | 124 days | 141 days |
| 2024 | 30 | 40 days | 114 days | 206 days |
| 2025 | 21 | 33 days | 79 days | 140 days |
| 2026* | 16 | 74 days | 111 days | 127 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context