Renovation & Alteration permits in ZIP 60628
The median renovation & alteration permit wait in ZIP 60628 was 41 days, based on 645 issued records.
Records checked6452021–Sep. 15, 2026
The short answer
Typical wait41 daysmedian issued permit
Usually within103 days75% of records
Long-wait edge183 days90% of records
Evidence645issued permits
The median was 11 days slower than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 126 | 7.5 days | 82 days | 172 days |
| 2022 | 138 | 5 days | 62 days | 167 days |
| 2023 | 104 | 20 days | 93 days | 194 days |
| 2024 | 93 | 55 days | 104 days | 181 days |
| 2025 | 113 | 64 days | 118 days | 176 days |
| 2026* | 71 | 69 days | 116 days | 161 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.