Renovation & Alteration permits in ZIP 60629
The median renovation & alteration permit wait in ZIP 60629 was 41 days, based on 571 issued records.
Records checked5712021–Sep. 15, 2026
The short answer
Typical wait41 daysmedian issued permit
Usually within110 days75% of records
Long-wait edge223 days90% of records
Evidence571issued permits
The median was 3 days slower than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 108 | 12 days | 65 days | 176 days |
| 2022 | 128 | 6 days | 53 days | 123 days |
| 2023 | 97 | 50 days | 131 days | 206 days |
| 2024 | 109 | 51 days | 119 days | 281 days |
| 2025 | 86 | 84 days | 215 days | 340 days |
| 2026* | 43 | 64 days | 155 days | 201 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.