Renovation & Alteration permits in ZIP 60653
The median renovation & alteration permit wait in ZIP 60653 was 41 days, based on 477 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Renovation & Alteration permits in ZIP 60653, 477 issued permit records show a median processing time of 41 days; 75% were issued within 135 days and 90% within 266 days, covering January 2021 through September 15, 2026.
The median was 77 days slower than the previous 12 months.
Renovation & Alteration permits in ZIP 60653: wait distribution
For Renovation & Alteration permits in ZIP 60653, 477 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Renovation & Alteration permits in ZIP 60653: annual permit timing
Renovation & Alteration permits in ZIP 60653 has 6 publishable issue-year cohorts spanning 2021–2026, representing 477 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 102 | 28 days | 110 days | 171 days |
| 2022 | 89 | 7 days | 96 days | 192 days |
| 2023 | 85 | 48 days | 136 days | 382 days |
| 2024 | 90 | 44 days | 131 days | 277 days |
| 2025 | 70 | 48 days | 152 days | 315 days |
| 2026* | 41 | 106 days | 143 days | 238 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Renovation & Alteration permits in ZIP 60653: Renovation & Alteration timing in comparable ZIP codes
Renovation & Alteration permits in ZIP 60653 has 477 issued records, a 41 days median, and a 135 days 75th-percentile wait in this release.
More Renovation & Alteration permits in ZIP 60653 comparisons
The Renovation & Alteration permits in ZIP 60653 cohort contains 477 issued records; related links retain separate location and permit-category cohorts.