ZIP boundary report
Permit processing times in ZIP 60653
Across 2,085 issued permits assigned to ZIP 60653, the median processing time was 4 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Permit processing times in ZIP 60653, 2,085 issued permit records show a median processing time of 4 days; 75% were issued within 29 days and 90% within 120 days, covering January 2021 through September 15, 2026.
The median was 7 days faster than the previous 12 months.
Permit processing times in ZIP 60653: wait distribution
For Permit processing times in ZIP 60653, 2,085 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Permit processing times in ZIP 60653: annual permit timing
Permit processing times in ZIP 60653 has 6 publishable issue-year cohorts spanning 2021–2026, representing 2,085 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 419 | 0 days | 32 days | 112 days |
| 2022 | 416 | 0 days | 13 days | 114 days |
| 2023 | 337 | 1 day | 35 days | 142 days |
| 2024 | 338 | 12 days | 36 days | 101 days |
| 2025 | 318 | 10 days | 36 days | 120 days |
| 2026* | 257 | 7 days | 34 days | 112 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Permit processing times in ZIP 60653: ZIP codes with similar overall timing
Permit processing times in ZIP 60653 has 2,085 issued records, a 4 days median, and a 29 days 75th-percentile wait in this release.
More Permit processing times in ZIP 60653 comparisons
The Permit processing times in ZIP 60653 cohort contains 2,085 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 3 daysRenovation & Alteration 41 daysEasy Permit Process 0 daysNew Construction 53 daysSigns 24 daysElevator Equipment 0 daysReinstated Permit 0 days