ZIP boundary report
Permit processing times in ZIP 60653
Across 2,085 issued permits assigned to ZIP 60653, the median processing time was 4 days.
Records checked2,0852021–Sep. 15, 2026
The short answer
Typical wait4 daysmedian issued permit
Usually within29 days75% of records
Long-wait edge120 days90% of records
Evidence2,085issued permits
The median was 7 days faster than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 419 | 0 days | 32 days | 112 days |
| 2022 | 416 | 0 days | 13 days | 114 days |
| 2023 | 337 | 1 day | 35 days | 142 days |
| 2024 | 338 | 12 days | 36 days | 101 days |
| 2025 | 318 | 10 days | 36 days | 120 days |
| 2026* | 257 | 7 days | 34 days | 112 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.