Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP code × permit type

New Construction permits in ZIP 60653

The median new construction permit wait in ZIP 60653 was 53 days, based on 214 issued records.

Records checked2142021–Sep. 15, 2026

The short answer

Typical wait53 daysmedian issued permit
Usually within110 days75% of records
Long-wait edge186 days90% of records
Evidence214issued permits

The median was 20 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
20.1%
1–7 days
6.1%
8–30 days
8.9%
31–90 days
33.6%
91+ days
31.3%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20214655 days107 days182 days
2022550 days116 days212 days
20233158 days145 days431 days
20243339 days91 days121 days
20253167 days83 days121 days
2026*1876 days88 days131 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction timing in comparable ZIP codes

ReportMedian75% withinRecords
ZIP 6063953 days119 days55
ZIP 6065353 days110 days214
ZIP 6070753 days156 days37
ZIP 6061552 days85 days154
ZIP 6064154 days124 days130
ZIP 6062452 days101 days162
ZIP 6065552 days103 days38
ZIP 6063252 days120 days122