New Construction permits in ZIP 60653
The median new construction permit wait in ZIP 60653 was 53 days, based on 214 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For New Construction permits in ZIP 60653, 214 issued permit records show a median processing time of 53 days; 75% were issued within 110 days and 90% within 186 days, covering January 2021 through September 15, 2026.
The median was 20 days slower than the previous 12 months.
New Construction permits in ZIP 60653: wait distribution
For New Construction permits in ZIP 60653, 214 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
New Construction permits in ZIP 60653: annual permit timing
New Construction permits in ZIP 60653 has 6 publishable issue-year cohorts spanning 2021–2026, representing 214 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 46 | 55 days | 107 days | 182 days |
| 2022 | 55 | 0 days | 116 days | 212 days |
| 2023 | 31 | 58 days | 145 days | 431 days |
| 2024 | 33 | 39 days | 91 days | 121 days |
| 2025 | 31 | 67 days | 83 days | 121 days |
| 2026* | 18 | 76 days | 88 days | 131 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction permits in ZIP 60653: New Construction timing in comparable ZIP codes
New Construction permits in ZIP 60653 has 214 issued records, a 53 days median, and a 110 days 75th-percentile wait in this release.
More New Construction permits in ZIP 60653 comparisons
The New Construction permits in ZIP 60653 cohort contains 214 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60653 permits ZIP reportNew Construction citywide Type report