New Construction permits in ZIP 60653
The median new construction permit wait in ZIP 60653 was 53 days, based on 214 issued records.
Records checked2142021–Sep. 15, 2026
The short answer
Typical wait53 daysmedian issued permit
Usually within110 days75% of records
Long-wait edge186 days90% of records
Evidence214issued permits
The median was 20 days slower than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 46 | 55 days | 107 days | 182 days |
| 2022 | 55 | 0 days | 116 days | 212 days |
| 2023 | 31 | 58 days | 145 days | 431 days |
| 2024 | 33 | 39 days | 91 days | 121 days |
| 2025 | 31 | 67 days | 83 days | 121 days |
| 2026* | 18 | 76 days | 88 days | 131 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context