ZIP code × permit type
New Construction permits in ZIP 60707
The median new construction permit wait in ZIP 60707 was 53 days, based on 37 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For New Construction permits in ZIP 60707, 37 issued permit records show a median processing time of 53 days; 75% were issued within 156 days and 90% within 259 days, covering January 2021 through September 15, 2026.
Not enough records for a year-over-year comparison.
New Construction permits in ZIP 60707: wait distribution
For New Construction permits in ZIP 60707, 37 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
New Construction permits in ZIP 60707: annual permit timing
New Construction permits in ZIP 60707 has 1 publishable issue-year cohorts spanning 2024–2024, representing 12 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2024 | 12 | 154 days | 245 days | 275 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction permits in ZIP 60707: New Construction timing in comparable ZIP codes
New Construction permits in ZIP 60707 has 37 issued records, a 53 days median, and a 156 days 75th-percentile wait in this release.
More New Construction permits in ZIP 60707 comparisons
The New Construction permits in ZIP 60707 cohort contains 37 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60707 permits ZIP reportNew Construction citywide Type report