ZIP code × permit type
New Construction permits in ZIP 60641
The median new construction permit wait in ZIP 60641 was 54 days, based on 130 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For New Construction permits in ZIP 60641, 130 issued permit records show a median processing time of 54 days; 75% were issued within 124 days and 90% within 277 days, covering January 2021 through September 15, 2026.
Not enough records for a year-over-year comparison.
New Construction permits in ZIP 60641: wait distribution
For New Construction permits in ZIP 60641, 130 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
New Construction permits in ZIP 60641: annual permit timing
New Construction permits in ZIP 60641 has 6 publishable issue-year cohorts spanning 2021–2026, representing 130 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 36 | 7 days | 104 days | 169 days |
| 2022 | 20 | 26 days | 187 days | 331 days |
| 2023 | 29 | 42 days | 107 days | 278 days |
| 2024 | 12 | 44 days | 126 days | 207 days |
| 2025 | 14 | 64 days | 105 days | 128 days |
| 2026* | 19 | 82 days | 154 days | 494 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction permits in ZIP 60641: New Construction timing in comparable ZIP codes
New Construction permits in ZIP 60641 has 130 issued records, a 54 days median, and a 124 days 75th-percentile wait in this release.
More New Construction permits in ZIP 60641 comparisons
The New Construction permits in ZIP 60641 cohort contains 130 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60641 permits ZIP reportNew Construction citywide Type report