New Construction permits in ZIP 60624
The median new construction permit wait in ZIP 60624 was 52 days, based on 162 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For New Construction permits in ZIP 60624, 162 issued permit records show a median processing time of 52 days; 75% were issued within 101 days and 90% within 175 days, covering January 2021 through September 15, 2026.
The median was 1 day slower than the previous 12 months.
New Construction permits in ZIP 60624: wait distribution
For New Construction permits in ZIP 60624, 162 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
New Construction permits in ZIP 60624: annual permit timing
New Construction permits in ZIP 60624 has 5 publishable issue-year cohorts spanning 2022–2026, representing 153 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2022 | 33 | 0 days | 22 days | 153 days |
| 2023 | 15 | 54 days | 92 days | 174 days |
| 2024 | 20 | 48 days | 122 days | 217 days |
| 2025 | 43 | 67 days | 110 days | 148 days |
| 2026* | 42 | 64 days | 110 days | 292 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction permits in ZIP 60624: New Construction timing in comparable ZIP codes
New Construction permits in ZIP 60624 has 162 issued records, a 52 days median, and a 101 days 75th-percentile wait in this release.
More New Construction permits in ZIP 60624 comparisons
The New Construction permits in ZIP 60624 cohort contains 162 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60624 permits ZIP reportNew Construction citywide Type report