ZIP boundary report
Permit processing times in ZIP 60611
Across 7,470 issued permits assigned to ZIP 60611, the median processing time was 4 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Permit processing times in ZIP 60611, 7,470 issued permit records show a median processing time of 4 days; 75% were issued within 15 days and 90% within 48 days, covering January 2021 through September 15, 2026.
The median was 1 day slower than the previous 12 months.
Permit processing times in ZIP 60611: wait distribution
For Permit processing times in ZIP 60611, 7,470 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Permit processing times in ZIP 60611: annual permit timing
Permit processing times in ZIP 60611 has 6 publishable issue-year cohorts spanning 2021–2026, representing 7,470 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 1,327 | 0 days | 9 days | 40 days |
| 2022 | 1,298 | 1 day | 13 days | 43 days |
| 2023 | 1,411 | 2 days | 15 days | 64 days |
| 2024 | 1,374 | 6 days | 22 days | 54 days |
| 2025 | 1,227 | 5 days | 15 days | 42 days |
| 2026* | 833 | 6 days | 18 days | 50 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Permit processing times in ZIP 60611: ZIP codes with similar overall timing
Permit processing times in ZIP 60611 has 7,470 issued records, a 4 days median, and a 15 days 75th-percentile wait in this release.
More Permit processing times in ZIP 60611 comparisons
The Permit processing times in ZIP 60611 cohort contains 7,470 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 3 daysRenovation & Alteration 10 daysElevator Equipment 0 daysEasy Permit Process 1 daySigns 30 daysScaffolding 0 daysNew Construction 5 days