Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP code × permit type

Easy Permit Process permits in ZIP 60611

The median easy permit process permit wait in ZIP 60611 was 1 day, based on 576 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked5762021–Sep. 15, 2026

The short answer

For Easy Permit Process permits in ZIP 60611, 576 issued permit records show a median processing time of 1 day; 75% were issued within 6.2 days and 90% within 15 days, covering January 2021 through September 15, 2026.

Typical wait1 daymedian issued permit
Usually within6.2 days75% of records
Long-wait edge15 days90% of records
Evidence576issued permits

Not enough records for a year-over-year comparison.

Easy Permit Process permits in ZIP 60611: wait distribution

For Easy Permit Process permits in ZIP 60611, 576 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
48.8%
1–7 days
30.2%
8–30 days
16.0%
31–90 days
4.2%
91+ days
0.9%

Change over time

Easy Permit Process permits in ZIP 60611: annual permit timing

Easy Permit Process permits in ZIP 60611 has 3 publishable issue-year cohorts spanning 2021–2023, representing 576 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20212140 days6 days14 days
20221931 day7 days14 days
20231691 day7 days20 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Easy Permit Process permits in ZIP 60611: Easy Permit Process timing in comparable ZIP codes

Easy Permit Process permits in ZIP 60611 has 576 issued records, a 1 day median, and a 6.2 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 606011 day6.2 days176
ZIP 606111 day6.2 days576
ZIP 606022 days8.2 days60
ZIP 606030 days5 days93
ZIP 606042 days7 days49
ZIP 606050 days3.8 days230
ZIP 606060 days2 days247
ZIP 606070 days1 day522