ZIP code × permit type
Signs permits in ZIP 60611
The median signs permit wait in ZIP 60611 was 30 days, based on 572 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Signs permits in ZIP 60611, 572 issued permit records show a median processing time of 30 days; 75% were issued within 63 days and 90% within 125 days, covering January 2021 through September 15, 2026.
The median was 8 days slower than the previous 12 months.
Signs permits in ZIP 60611: wait distribution
For Signs permits in ZIP 60611, 572 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Signs permits in ZIP 60611: annual permit timing
Signs permits in ZIP 60611 has 6 publishable issue-year cohorts spanning 2021–2026, representing 572 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 64 | 40 days | 90 days | 151 days |
| 2022 | 107 | 16 days | 43 days | 77 days |
| 2023 | 105 | 17 days | 62 days | 98 days |
| 2024 | 123 | 39 days | 74 days | 182 days |
| 2025 | 109 | 32 days | 43 days | 63 days |
| 2026* | 64 | 47 days | 94 days | 192 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Signs permits in ZIP 60611: Signs timing in comparable ZIP codes
Signs permits in ZIP 60611 has 572 issued records, a 30 days median, and a 63 days 75th-percentile wait in this release.
More Signs permits in ZIP 60611 comparisons
The Signs permits in ZIP 60611 cohort contains 572 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60611 permits ZIP reportSigns citywide Type report