ZIP code × permit type
Signs permits in ZIP 60622
The median signs permit wait in ZIP 60622 was 29 days, based on 331 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Signs permits in ZIP 60622, 331 issued permit records show a median processing time of 29 days; 75% were issued within 84 days and 90% within 195 days, covering January 2021 through September 15, 2026.
The median was 14 days slower than the previous 12 months.
Signs permits in ZIP 60622: wait distribution
For Signs permits in ZIP 60622, 331 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Signs permits in ZIP 60622: annual permit timing
Signs permits in ZIP 60622 has 6 publishable issue-year cohorts spanning 2021–2026, representing 331 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 32 | 88 days | 245 days | 552 days |
| 2022 | 100 | 4 days | 15 days | 121 days |
| 2023 | 41 | 18 days | 81 days | 591 days |
| 2024 | 62 | 40 days | 79 days | 128 days |
| 2025 | 70 | 45 days | 119 days | 212 days |
| 2026* | 26 | 43 days | 88 days | 128 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Signs permits in ZIP 60622: Signs timing in comparable ZIP codes
Signs permits in ZIP 60622 has 331 issued records, a 29 days median, and a 84 days 75th-percentile wait in this release.
More Signs permits in ZIP 60622 comparisons
The Signs permits in ZIP 60622 cohort contains 331 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60622 permits ZIP reportSigns citywide Type report