Signs permits in ZIP 60616
The median signs permit wait in ZIP 60616 was 29 days, based on 205 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Signs permits in ZIP 60616, 205 issued permit records show a median processing time of 29 days; 75% were issued within 74 days and 90% within 130 days, covering January 2021 through September 15, 2026.
The median was 1 day faster than the previous 12 months.
Signs permits in ZIP 60616: wait distribution
For Signs permits in ZIP 60616, 205 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Signs permits in ZIP 60616: annual permit timing
Signs permits in ZIP 60616 has 6 publishable issue-year cohorts spanning 2021–2026, representing 205 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 43 | 12 days | 120 days | 182 days |
| 2022 | 31 | 21 days | 81 days | 224 days |
| 2023 | 42 | 21 days | 89 days | 117 days |
| 2024 | 28 | 53 days | 64 days | 112 days |
| 2025 | 38 | 26 days | 45 days | 82 days |
| 2026* | 23 | 31 days | 36 days | 53 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Signs permits in ZIP 60616: Signs timing in comparable ZIP codes
Signs permits in ZIP 60616 has 205 issued records, a 29 days median, and a 74 days 75th-percentile wait in this release.