ZIP boundary report
Permit processing times in ZIP 60654
Across 3,185 issued permits assigned to ZIP 60654, the median processing time was 4 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Permit processing times in ZIP 60654, 3,185 issued permit records show a median processing time of 4 days; 75% were issued within 27 days and 90% within 79 days, covering January 2021 through September 15, 2026.
The median was unchanged from the previous 12 months.
Permit processing times in ZIP 60654: wait distribution
For Permit processing times in ZIP 60654, 3,185 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Permit processing times in ZIP 60654: annual permit timing
Permit processing times in ZIP 60654 has 6 publishable issue-year cohorts spanning 2021–2026, representing 3,185 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 534 | 1 day | 17 days | 83 days |
| 2022 | 596 | 0 days | 16 days | 73 days |
| 2023 | 548 | 1.5 days | 29 days | 94 days |
| 2024 | 593 | 11 days | 35 days | 96 days |
| 2025 | 553 | 5 days | 21 days | 55 days |
| 2026* | 361 | 7 days | 28 days | 84 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Permit processing times in ZIP 60654: ZIP codes with similar overall timing
Permit processing times in ZIP 60654 has 3,185 issued records, a 4 days median, and a 27 days 75th-percentile wait in this release.
More Permit processing times in ZIP 60654 comparisons
The Permit processing times in ZIP 60654 cohort contains 3,185 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 2 daysRenovation & Alteration 9 daysSigns 32 daysElevator Equipment 0 daysEasy Permit Process 0 daysNew Construction 13 daysScaffolding 0 days