Renovation & Alteration permits in ZIP 60654
The median renovation & alteration permit wait in ZIP 60654 was 9 days, based on 667 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Renovation & Alteration permits in ZIP 60654, 667 issued permit records show a median processing time of 9 days; 75% were issued within 42 days and 90% within 99 days, covering January 2021 through September 15, 2026.
The median was 1.5 days slower than the previous 12 months.
Renovation & Alteration permits in ZIP 60654: wait distribution
For Renovation & Alteration permits in ZIP 60654, 667 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Renovation & Alteration permits in ZIP 60654: annual permit timing
Renovation & Alteration permits in ZIP 60654 has 6 publishable issue-year cohorts spanning 2021–2026, representing 667 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 115 | 0 days | 33 days | 124 days |
| 2022 | 132 | 0 days | 0 days | 64 days |
| 2023 | 109 | 2 days | 49 days | 97 days |
| 2024 | 128 | 32 days | 55 days | 111 days |
| 2025 | 118 | 19 days | 47 days | 92 days |
| 2026* | 65 | 21 days | 38 days | 128 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Renovation & Alteration permits in ZIP 60654: Renovation & Alteration timing in comparable ZIP codes
Renovation & Alteration permits in ZIP 60654 has 667 issued records, a 9 days median, and a 42 days 75th-percentile wait in this release.
More Renovation & Alteration permits in ZIP 60654 comparisons
The Renovation & Alteration permits in ZIP 60654 cohort contains 667 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60654 permits ZIP reportRenovation & Alteration citywide Type report