Renovation & Alteration permits in ZIP 60611
The median renovation & alteration permit wait in ZIP 60611 was 10 days, based on 1,172 issued records.
Records checked1,1722021–Sep. 15, 2026
The short answer
Typical wait10 daysmedian issued permit
Usually within45 days75% of records
Long-wait edge95 days90% of records
Evidence1,172issued permits
The median was 5.5 days slower than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 211 | 0 days | 18 days | 74 days |
| 2022 | 230 | 0 days | 29 days | 76 days |
| 2023 | 205 | 2 days | 39 days | 78 days |
| 2024 | 167 | 23 days | 52 days | 107 days |
| 2025 | 207 | 23 days | 54 days | 104 days |
| 2026* | 152 | 32 days | 57 days | 117 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context