Renovation & Alteration permits in ZIP 60634
The median renovation & alteration permit wait in ZIP 60634 was 43 days, based on 457 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Renovation & Alteration permits in ZIP 60634, 457 issued permit records show a median processing time of 43 days; 75% were issued within 109 days and 90% within 199 days, covering January 2021 through September 15, 2026.
The median was 3.5 days slower than the previous 12 months.
Renovation & Alteration permits in ZIP 60634: wait distribution
For Renovation & Alteration permits in ZIP 60634, 457 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Renovation & Alteration permits in ZIP 60634: annual permit timing
Renovation & Alteration permits in ZIP 60634 has 6 publishable issue-year cohorts spanning 2021–2026, representing 457 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 96 | 5 days | 50 days | 136 days |
| 2022 | 88 | 1 day | 65 days | 126 days |
| 2023 | 87 | 48 days | 124 days | 194 days |
| 2024 | 72 | 68 days | 128 days | 227 days |
| 2025 | 70 | 70 days | 140 days | 225 days |
| 2026* | 44 | 72 days | 138 days | 251 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Renovation & Alteration permits in ZIP 60634: Renovation & Alteration timing in comparable ZIP codes
Renovation & Alteration permits in ZIP 60634 has 457 issued records, a 43 days median, and a 109 days 75th-percentile wait in this release.
More Renovation & Alteration permits in ZIP 60634 comparisons
The Renovation & Alteration permits in ZIP 60634 cohort contains 457 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60634 permits ZIP reportRenovation & Alteration citywide Type report