Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP boundary report

Permit processing times in ZIP 60634

Across 3,384 issued permits assigned to ZIP 60634, the median processing time was 0 days.

Records checked3,3842021–Sep. 15, 2026

The short answer

Typical wait0 daysmedian issued permit
Usually within10 days75% of records
Long-wait edge43 days90% of records
Evidence3,384issued permits

The median was unchanged from the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
52.0%
1–7 days
19.7%
8–30 days
15.6%
31–90 days
6.7%
91+ days
6.1%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20216720 days6 days24 days
20226640 days5 days23 days
20235540 days11 days49 days
20245881 day12 days43 days
20255563 days13 days63 days
2026*3503 days14 days55 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

ZIP codes with similar overall timing

ReportMedian75% withinRecords
606290 days11 days4,601
606310 days14 days2,923
606330 days4 days950
606340 days10 days3,384
606460 days13 days1,764
606560 days8 days1,055
606660 days4 days397
606021 day10 days1,991