Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP boundary report

Permit processing times in ZIP 60602

Across 1,991 issued permits assigned to ZIP 60602, the median processing time was 1 day.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked1,9912021–Sep. 15, 2026

The short answer

For Permit processing times in ZIP 60602, 1,991 issued permit records show a median processing time of 1 day; 75% were issued within 10 days and 90% within 38 days, covering January 2021 through September 15, 2026.

Typical wait1 daymedian issued permit
Usually within10 days75% of records
Long-wait edge38 days90% of records
Evidence1,991issued permits

The median was 2 days slower than the previous 12 months.

Permit processing times in ZIP 60602: wait distribution

For Permit processing times in ZIP 60602, 1,991 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
44.9%
1–7 days
27.2%
8–30 days
16.3%
31–90 days
8.9%
91+ days
2.8%

Change over time

Permit processing times in ZIP 60602: annual permit timing

Permit processing times in ZIP 60602 has 6 publishable issue-year cohorts spanning 2021–2026, representing 1,991 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20212980 days10 days41 days
20224020 days7 days37 days
20233511 day20 days61 days
20243292 days14 days49 days
20253812 days7 days22 days
2026*2303 days7 days19 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Permit processing times in ZIP 60602: ZIP codes with similar overall timing

Permit processing times in ZIP 60602 has 1,991 issued records, a 1 day median, and a 10 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
606021 day10 days1,991
606031 day13 days1,858
606051 day16 days2,380
606091 day21 days3,840
606121 day25 days3,771
606171 day11 days4,812
606191 day12 days5,016
606201 day11 days5,084