Permit processing times in ZIP 60605
Across 2,380 issued permits assigned to ZIP 60605, the median processing time was 1 day.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Permit processing times in ZIP 60605, 2,380 issued permit records show a median processing time of 1 day; 75% were issued within 16 days and 90% within 59 days, covering January 2021 through September 15, 2026.
The median was 1 day slower than the previous 12 months.
Permit processing times in ZIP 60605: wait distribution
For Permit processing times in ZIP 60605, 2,380 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Permit processing times in ZIP 60605: annual permit timing
Permit processing times in ZIP 60605 has 6 publishable issue-year cohorts spanning 2021–2026, representing 2,380 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 436 | 0 days | 7 days | 56 days |
| 2022 | 420 | 0 days | 12 days | 51 days |
| 2023 | 449 | 0 days | 14 days | 78 days |
| 2024 | 408 | 4 days | 18 days | 59 days |
| 2025 | 364 | 5 days | 18 days | 62 days |
| 2026* | 303 | 5 days | 21 days | 48 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Permit processing times in ZIP 60605: ZIP codes with similar overall timing
Permit processing times in ZIP 60605 has 2,380 issued records, a 1 day median, and a 16 days 75th-percentile wait in this release.
More Permit processing times in ZIP 60605 comparisons
The Permit processing times in ZIP 60605 cohort contains 2,380 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 1 dayRenovation & Alteration 27 daysNew Construction 1 dayEasy Permit Process 0 daysSigns 44 daysElevator Equipment 0 daysScaffolding 0 daysReinstated Permit 0 days