Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP boundary report

Permit processing times in ZIP 60609

Across 3,840 issued permits assigned to ZIP 60609, the median processing time was 1 day.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked3,8402021–Sep. 15, 2026

The short answer

For Permit processing times in ZIP 60609, 3,840 issued permit records show a median processing time of 1 day; 75% were issued within 21 days and 90% within 106 days, covering January 2021 through September 15, 2026.

Typical wait1 daymedian issued permit
Usually within21 days75% of records
Long-wait edge106 days90% of records
Evidence3,840issued permits

The median was 5 days faster than the previous 12 months.

Permit processing times in ZIP 60609: wait distribution

For Permit processing times in ZIP 60609, 3,840 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
45.1%
1–7 days
19.0%
8–30 days
14.7%
31–90 days
9.8%
91+ days
11.4%

Change over time

Permit processing times in ZIP 60609: annual permit timing

Permit processing times in ZIP 60609 has 6 publishable issue-year cohorts spanning 2021–2026, representing 3,840 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20217550 days8 days58 days
20227660 days5 days72 days
20236690 days11 days81 days
20245587 days36 days152 days
20256519 days41 days141 days
2026*4416 days39 days136 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Permit processing times in ZIP 60609: ZIP codes with similar overall timing

Permit processing times in ZIP 60609 has 3,840 issued records, a 1 day median, and a 21 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
606021 day10 days1,991
606031 day13 days1,858
606051 day16 days2,380
606091 day21 days3,840
606121 day25 days3,771
606171 day11 days4,812
606191 day12 days5,016
606201 day11 days5,084