Wrecking & Demolition permits in ZIP 60609
The median wrecking & demolition permit wait in ZIP 60609 was 0 days, based on 151 issued records.
Records checked1512021–Sep. 15, 2026
The short answer
Typical wait0 daysmedian issued permit
Usually within48 days75% of records
Long-wait edge109 days90% of records
Evidence151issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 31 | 48 days | 122 days | 201 days |
| 2022 | 42 | 0 days | 75 days | 142 days |
| 2023 | 25 | 0 days | 0 days | 0 days |
| 2024 | 25 | 0 days | 0 days | 0 days |
| 2025 | 19 | 0 days | 0 days | 0 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.