ZIP code × permit type
Wrecking & Demolition permits in ZIP 60614
The median wrecking & demolition permit wait in ZIP 60614 was 0 days, based on 270 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Wrecking & Demolition permits in ZIP 60614, 270 issued permit records show a median processing time of 0 days; 75% were issued within 60 days and 90% within 111 days, covering January 2021 through September 15, 2026.
The median was 28 days slower than the previous 12 months.
Wrecking & Demolition permits in ZIP 60614: wait distribution
For Wrecking & Demolition permits in ZIP 60614, 270 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Wrecking & Demolition permits in ZIP 60614: annual permit timing
Wrecking & Demolition permits in ZIP 60614 has 6 publishable issue-year cohorts spanning 2021–2026, representing 270 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 57 | 57 days | 77 days | 109 days |
| 2022 | 55 | 0 days | 78 days | 128 days |
| 2023 | 35 | 0 days | 0 days | 0 days |
| 2024 | 39 | 0 days | 0 days | 91 days |
| 2025 | 45 | 0 days | 0 days | 0 days |
| 2026* | 39 | 63 days | 114 days | 139 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Wrecking & Demolition permits in ZIP 60614: Wrecking & Demolition timing in comparable ZIP codes
Wrecking & Demolition permits in ZIP 60614 has 270 issued records, a 0 days median, and a 60 days 75th-percentile wait in this release.
More Wrecking & Demolition permits in ZIP 60614 comparisons
The Wrecking & Demolition permits in ZIP 60614 cohort contains 270 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60614 permits ZIP reportWrecking & Demolition citywide Type report