ZIP code × permit type
Wrecking & Demolition permits in ZIP 60617
The median wrecking & demolition permit wait in ZIP 60617 was 0 days, based on 118 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Wrecking & Demolition permits in ZIP 60617, 118 issued permit records show a median processing time of 0 days; 75% were issued within 24 days and 90% within 85 days, covering January 2021 through September 15, 2026.
Not enough records for a year-over-year comparison.
Wrecking & Demolition permits in ZIP 60617: wait distribution
For Wrecking & Demolition permits in ZIP 60617, 118 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Wrecking & Demolition permits in ZIP 60617: annual permit timing
Wrecking & Demolition permits in ZIP 60617 has 5 publishable issue-year cohorts spanning 2021–2025, representing 111 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 27 | 44 days | 66 days | 114 days |
| 2022 | 29 | 0 days | 0 days | 188 days |
| 2023 | 15 | 0 days | 18 days | 36 days |
| 2024 | 21 | 0 days | 0 days | 0 days |
| 2025 | 19 | 0 days | 0 days | 0 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Wrecking & Demolition permits in ZIP 60617: Wrecking & Demolition timing in comparable ZIP codes
Wrecking & Demolition permits in ZIP 60617 has 118 issued records, a 0 days median, and a 24 days 75th-percentile wait in this release.
More Wrecking & Demolition permits in ZIP 60617 comparisons
The Wrecking & Demolition permits in ZIP 60617 cohort contains 118 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60617 permits ZIP reportWrecking & Demolition citywide Type report