ZIP boundary report
Permit processing times in ZIP 60617
Across 4,812 issued permits assigned to ZIP 60617, the median processing time was 1 day.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Permit processing times in ZIP 60617, 4,812 issued permit records show a median processing time of 1 day; 75% were issued within 11 days and 90% within 47 days, covering January 2021 through September 15, 2026.
The median was 0.5 days slower than the previous 12 months.
Permit processing times in ZIP 60617: wait distribution
For Permit processing times in ZIP 60617, 4,812 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Permit processing times in ZIP 60617: annual permit timing
Permit processing times in ZIP 60617 has 6 publishable issue-year cohorts spanning 2021–2026, representing 4,812 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 966 | 0 days | 6 days | 34 days |
| 2022 | 926 | 0 days | 5 days | 36 days |
| 2023 | 745 | 0 days | 11 days | 36 days |
| 2024 | 793 | 2 days | 14 days | 55 days |
| 2025 | 846 | 3 days | 15 days | 50 days |
| 2026* | 536 | 4 days | 15 days | 72 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Permit processing times in ZIP 60617: ZIP codes with similar overall timing
Permit processing times in ZIP 60617 has 4,812 issued records, a 1 day median, and a 11 days 75th-percentile wait in this release.
More Permit processing times in ZIP 60617 comparisons
The Permit processing times in ZIP 60617 cohort contains 4,812 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 0 daysEasy Permit Process 0 daysRenovation & Alteration 36 daysSigns 13 daysWrecking & Demolition 0 daysElevator Equipment 0 daysNew Construction 78 daysReinstated Permit 0 days