ZIP code × permit type
New Construction permits in ZIP 60617
The median new construction permit wait in ZIP 60617 was 78 days, based on 44 issued records.
Records checked442021–Sep. 15, 2026
The short answer
Typical wait78 daysmedian issued permit
Usually within212 days75% of records
Long-wait edge296 days90% of records
Evidence44issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 10 | 22 days | 84 days | 183 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context