ZIP code × permit type
New Construction permits in ZIP 60644
The median new construction permit wait in ZIP 60644 was 71 days, based on 91 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For New Construction permits in ZIP 60644, 91 issued permit records show a median processing time of 71 days; 75% were issued within 140 days and 90% within 230 days, covering January 2021 through September 15, 2026.
Not enough records for a year-over-year comparison.
New Construction permits in ZIP 60644: wait distribution
For New Construction permits in ZIP 60644, 91 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
New Construction permits in ZIP 60644: annual permit timing
New Construction permits in ZIP 60644 has 5 publishable issue-year cohorts spanning 2022–2026, representing 84 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2022 | 25 | 32 days | 113 days | 200 days |
| 2023 | 15 | 83 days | 180 days | 213 days |
| 2024 | 11 | 57 days | 152 days | 230 days |
| 2025 | 19 | 64 days | 110 days | 156 days |
| 2026* | 14 | 91 days | 171 days | 295 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction permits in ZIP 60644: New Construction timing in comparable ZIP codes
New Construction permits in ZIP 60644 has 91 issued records, a 71 days median, and a 140 days 75th-percentile wait in this release.
More New Construction permits in ZIP 60644 comparisons
The New Construction permits in ZIP 60644 cohort contains 91 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60644 permits ZIP reportNew Construction citywide Type report