New Construction permits in ZIP 60660
The median new construction permit wait in ZIP 60660 was 62 days, based on 81 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For New Construction permits in ZIP 60660, 81 issued permit records show a median processing time of 62 days; 75% were issued within 101 days and 90% within 168 days, covering January 2021 through September 15, 2026.
Not enough records for a year-over-year comparison.
New Construction permits in ZIP 60660: wait distribution
For New Construction permits in ZIP 60660, 81 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
New Construction permits in ZIP 60660: annual permit timing
New Construction permits in ZIP 60660 has 5 publishable issue-year cohorts spanning 2021–2026, representing 72 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 12 | 28 days | 123 days | 325 days |
| 2022 | 18 | 61 days | 62 days | 75 days |
| 2023 | 22 | 80 days | 101 days | 117 days |
| 2025 | 10 | 56 days | 110 days | 167 days |
| 2026* | 10 | 60 days | 96 days | 130 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction permits in ZIP 60660: New Construction timing in comparable ZIP codes
New Construction permits in ZIP 60660 has 81 issued records, a 62 days median, and a 101 days 75th-percentile wait in this release.
More New Construction permits in ZIP 60660 comparisons
The New Construction permits in ZIP 60660 cohort contains 81 issued records; related links retain separate location and permit-category cohorts.