New Construction permits in ZIP 60651
The median new construction permit wait in ZIP 60651 was 57 days, based on 151 issued records.
Records checked1512021–Sep. 15, 2026
The short answer
Typical wait57 daysmedian issued permit
Usually within114 days75% of records
Long-wait edge238 days90% of records
Evidence151issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 42 | 29 days | 66 days | 126 days |
| 2022 | 20 | 22 days | 107 days | 396 days |
| 2023 | 21 | 89 days | 168 days | 327 days |
| 2024 | 20 | 48 days | 115 days | 190 days |
| 2025 | 35 | 66 days | 113 days | 224 days |
| 2026* | 13 | 113 days | 190 days | 278 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.