Permit processing times in ZIP 60651
Across 3,494 issued permits assigned to ZIP 60651, the median processing time was 1 day.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Permit processing times in ZIP 60651, 3,494 issued permit records show a median processing time of 1 day; 75% were issued within 15 days and 90% within 75 days, covering January 2021 through September 15, 2026.
The median was unchanged from the previous 12 months.
Permit processing times in ZIP 60651: wait distribution
For Permit processing times in ZIP 60651, 3,494 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Permit processing times in ZIP 60651: annual permit timing
Permit processing times in ZIP 60651 has 6 publishable issue-year cohorts spanning 2021–2026, representing 3,494 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 713 | 0 days | 5 days | 56 days |
| 2022 | 660 | 0 days | 7 days | 50 days |
| 2023 | 632 | 0 days | 10 days | 59 days |
| 2024 | 512 | 4 days | 26 days | 93 days |
| 2025 | 575 | 6 days | 33 days | 96 days |
| 2026* | 402 | 6.5 days | 37 days | 99 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Permit processing times in ZIP 60651: ZIP codes with similar overall timing
Permit processing times in ZIP 60651 has 3,494 issued records, a 1 day median, and a 15 days 75th-percentile wait in this release.
More Permit processing times in ZIP 60651 comparisons
The Permit processing times in ZIP 60651 cohort contains 3,494 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 1 dayEasy Permit Process 0 daysRenovation & Alteration 37 daysSigns 17 daysNew Construction 57 daysElevator Equipment 0 daysWrecking & Demolition 0 daysReinstated Permit 0 days