Renovation & Alteration permits in ZIP 60651
The median renovation & alteration permit wait in ZIP 60651 was 37 days, based on 720 issued records.
Records checked7202021–Sep. 15, 2026
The short answer
Typical wait37 daysmedian issued permit
Usually within102 days75% of records
Long-wait edge200 days90% of records
Evidence720issued permits
The median was 10 days slower than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 138 | 2 days | 62 days | 178 days |
| 2022 | 154 | 7.5 days | 70 days | 140 days |
| 2023 | 121 | 21 days | 71 days | 171 days |
| 2024 | 119 | 56 days | 130 days | 199 days |
| 2025 | 107 | 64 days | 153 days | 256 days |
| 2026* | 81 | 71 days | 134 days | 227 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context