Renovation & Alteration permits in ZIP 60641
The median renovation & alteration permit wait in ZIP 60641 was 37 days, based on 682 issued records.
Records checked6822021–Sep. 15, 2026
The short answer
Typical wait37 daysmedian issued permit
Usually within96 days75% of records
Long-wait edge179 days90% of records
Evidence682issued permits
The median was 2 days faster than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 131 | 1 day | 55 days | 113 days |
| 2022 | 134 | 3 days | 66 days | 168 days |
| 2023 | 137 | 28 days | 80 days | 161 days |
| 2024 | 110 | 54 days | 122 days | 230 days |
| 2025 | 101 | 64 days | 99 days | 177 days |
| 2026* | 69 | 61 days | 153 days | 210 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.