ZIP code × permit type
Renovation & Alteration permits in ZIP 60633
The median renovation & alteration permit wait in ZIP 60633 was 38 days, based on 52 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Renovation & Alteration permits in ZIP 60633, 52 issued permit records show a median processing time of 38 days; 75% were issued within 109 days and 90% within 173 days, covering January 2021 through September 15, 2026.
Not enough records for a year-over-year comparison.
Renovation & Alteration permits in ZIP 60633: wait distribution
For Renovation & Alteration permits in ZIP 60633, 52 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Renovation & Alteration permits in ZIP 60633: annual permit timing
Renovation & Alteration permits in ZIP 60633 has 3 publishable issue-year cohorts spanning 2021–2023, representing 37 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 13 | 0 days | 35 days | 81 days |
| 2022 | 13 | 47 days | 114 days | 163 days |
| 2023 | 11 | 66 days | 166 days | 207 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Renovation & Alteration permits in ZIP 60633: Renovation & Alteration timing in comparable ZIP codes
Renovation & Alteration permits in ZIP 60633 has 52 issued records, a 38 days median, and a 109 days 75th-percentile wait in this release.
More Renovation & Alteration permits in ZIP 60633 comparisons
The Renovation & Alteration permits in ZIP 60633 cohort contains 52 issued records; related links retain separate location and permit-category cohorts.