ZIP code × permit type
Renovation & Alteration permits in ZIP 60612
The median renovation & alteration permit wait in ZIP 60612 was 35 days, based on 779 issued records.
Records checked7792021–Sep. 15, 2026
The short answer
Typical wait35 daysmedian issued permit
Usually within98 days75% of records
Long-wait edge183 days90% of records
Evidence779issued permits
The median was 24 days slower than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 145 | 2 days | 48 days | 126 days |
| 2022 | 164 | 5 days | 57 days | 140 days |
| 2023 | 128 | 26 days | 97 days | 182 days |
| 2024 | 144 | 50 days | 136 days | 273 days |
| 2025 | 119 | 54 days | 98 days | 160 days |
| 2026* | 79 | 90 days | 150 days | 263 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.