Renovation & Alteration permits in ZIP 60624
The median renovation & alteration permit wait in ZIP 60624 was 34 days, based on 753 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Renovation & Alteration permits in ZIP 60624, 753 issued permit records show a median processing time of 34 days; 75% were issued within 91 days and 90% within 191 days, covering January 2021 through September 15, 2026.
The median was 21 days slower than the previous 12 months.
Renovation & Alteration permits in ZIP 60624: wait distribution
For Renovation & Alteration permits in ZIP 60624, 753 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Renovation & Alteration permits in ZIP 60624: annual permit timing
Renovation & Alteration permits in ZIP 60624 has 6 publishable issue-year cohorts spanning 2021–2026, representing 753 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 159 | 3 days | 52 days | 140 days |
| 2022 | 175 | 7 days | 52 days | 172 days |
| 2023 | 105 | 20 days | 84 days | 212 days |
| 2024 | 132 | 53 days | 119 days | 177 days |
| 2025 | 120 | 65 days | 97 days | 238 days |
| 2026* | 62 | 79 days | 155 days | 216 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Renovation & Alteration permits in ZIP 60624: Renovation & Alteration timing in comparable ZIP codes
Renovation & Alteration permits in ZIP 60624 has 753 issued records, a 34 days median, and a 91 days 75th-percentile wait in this release.
More Renovation & Alteration permits in ZIP 60624 comparisons
The Renovation & Alteration permits in ZIP 60624 cohort contains 753 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60624 permits ZIP reportRenovation & Alteration citywide Type report