Renovation & Alteration permits in ZIP 60626
The median renovation & alteration permit wait in ZIP 60626 was 34 days, based on 356 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Renovation & Alteration permits in ZIP 60626, 356 issued permit records show a median processing time of 34 days; 75% were issued within 81 days and 90% within 154 days, covering January 2021 through September 15, 2026.
The median was 5 days faster than the previous 12 months.
Renovation & Alteration permits in ZIP 60626: wait distribution
For Renovation & Alteration permits in ZIP 60626, 356 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Renovation & Alteration permits in ZIP 60626: annual permit timing
Renovation & Alteration permits in ZIP 60626 has 6 publishable issue-year cohorts spanning 2021–2026, representing 356 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 66 | 6 days | 60 days | 118 days |
| 2022 | 74 | 3 days | 51 days | 112 days |
| 2023 | 68 | 24 days | 72 days | 112 days |
| 2024 | 68 | 44 days | 92 days | 153 days |
| 2025 | 44 | 57 days | 112 days | 236 days |
| 2026* | 36 | 78 days | 140 days | 158 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Renovation & Alteration permits in ZIP 60626: Renovation & Alteration timing in comparable ZIP codes
Renovation & Alteration permits in ZIP 60626 has 356 issued records, a 34 days median, and a 81 days 75th-percentile wait in this release.
More Renovation & Alteration permits in ZIP 60626 comparisons
The Renovation & Alteration permits in ZIP 60626 cohort contains 356 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60626 permits ZIP reportRenovation & Alteration citywide Type report