Renovation & Alteration permits in ZIP 60619
The median renovation & alteration permit wait in ZIP 60619 was 33 days, based on 967 issued records.
Records checked9672021–Sep. 15, 2026
The short answer
Typical wait33 daysmedian issued permit
Usually within90 days75% of records
Long-wait edge181 days90% of records
Evidence967issued permits
The median was 36 days slower than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 201 | 5 days | 47 days | 132 days |
| 2022 | 203 | 7 days | 76 days | 156 days |
| 2023 | 194 | 39 days | 100 days | 208 days |
| 2024 | 171 | 41 days | 98 days | 223 days |
| 2025 | 117 | 51 days | 97 days | 174 days |
| 2026* | 81 | 84 days | 142 days | 238 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context