ZIP boundary report
Permit processing times in ZIP 60619
Across 5,016 issued permits assigned to ZIP 60619, the median processing time was 1 day.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Permit processing times in ZIP 60619, 5,016 issued permit records show a median processing time of 1 day; 75% were issued within 12 days and 90% within 56 days, covering January 2021 through September 15, 2026.
The median was unchanged from the previous 12 months.
Permit processing times in ZIP 60619: wait distribution
For Permit processing times in ZIP 60619, 5,016 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Permit processing times in ZIP 60619: annual permit timing
Permit processing times in ZIP 60619 has 6 publishable issue-year cohorts spanning 2021–2026, representing 5,016 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 1,020 | 0 days | 3 days | 27 days |
| 2022 | 994 | 0 days | 6 days | 43 days |
| 2023 | 844 | 0 days | 11 days | 66 days |
| 2024 | 817 | 4 days | 20 days | 68 days |
| 2025 | 805 | 5 days | 17 days | 59 days |
| 2026* | 536 | 4.5 days | 19 days | 80 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Permit processing times in ZIP 60619: ZIP codes with similar overall timing
Permit processing times in ZIP 60619 has 5,016 issued records, a 1 day median, and a 12 days 75th-percentile wait in this release.
More Permit processing times in ZIP 60619 comparisons
The Permit processing times in ZIP 60619 cohort contains 5,016 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 1 dayEasy Permit Process 0 daysRenovation & Alteration 33 daysSigns 26 daysWrecking & Demolition 0 daysReinstated Permit 0 daysElevator Equipment 0 daysNew Construction 44 days