Renovation & Alteration permits in ZIP 60615
The median renovation & alteration permit wait in ZIP 60615 was 32 days, based on 588 issued records.
Records checked5882021–Sep. 15, 2026
The short answer
Typical wait32 daysmedian issued permit
Usually within90 days75% of records
Long-wait edge158 days90% of records
Evidence588issued permits
The median was 1.5 days faster than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 105 | 2 days | 43 days | 82 days |
| 2022 | 112 | 3.5 days | 54 days | 113 days |
| 2023 | 119 | 43 days | 98 days | 184 days |
| 2024 | 103 | 50 days | 95 days | 210 days |
| 2025 | 93 | 56 days | 114 days | 169 days |
| 2026* | 56 | 58 days | 126 days | 192 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.