ZIP boundary report

Permit processing times in ZIP 60615

Across 2,792 issued permits assigned to ZIP 60615, the median processing time was 3 days.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked2,7922021–Sep. 15, 2026

The short answer

For Permit processing times in ZIP 60615, 2,792 issued permit records show a median processing time of 3 days; 75% were issued within 22 days and 90% within 79 days, covering January 2021 through September 15, 2026.

Typical wait3 daysmedian issued permit
Usually within22 days75% of records
Long-wait edge79 days90% of records
Evidence2,792issued permits

The median was 2 days faster than the previous 12 months.

Permit processing times in ZIP 60615: wait distribution

For Permit processing times in ZIP 60615, 2,792 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
38.3%
1–7 days
22.7%
8–30 days
18.6%
31–90 days
11.9%
91+ days
8.6%

Change over time

Permit processing times in ZIP 60615: annual permit timing

Permit processing times in ZIP 60615 has 6 publishable issue-year cohorts spanning 2021–2026, representing 2,792 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20215160 days9.2 days54 days
20224970 days7 days55 days
20235000 days18 days87 days
20244839 days30 days89 days
20254889 days37 days96 days
2026*3087 days29 days95 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Permit processing times in ZIP 60615: ZIP codes with similar overall timing

Permit processing times in ZIP 60615 has 2,792 issued records, a 3 days median, and a 22 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
606013 days15 days3,363
606043 days17 days1,054
606143 days28 days6,952
606153 days22 days2,792
606062 days15 days6,775
606082 days26 days4,677
606132 days21 days2,994
606162 days25 days2,939