ZIP boundary report
Permit processing times in ZIP 60614
Across 6,952 issued permits assigned to ZIP 60614, the median processing time was 3 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Permit processing times in ZIP 60614, 6,952 issued permit records show a median processing time of 3 days; 75% were issued within 28 days and 90% within 87 days, covering January 2021 through September 15, 2026.
The median was 2 days faster than the previous 12 months.
Permit processing times in ZIP 60614: wait distribution
For Permit processing times in ZIP 60614, 6,952 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Permit processing times in ZIP 60614: annual permit timing
Permit processing times in ZIP 60614 has 6 publishable issue-year cohorts spanning 2021–2026, representing 6,952 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 1,415 | 0 days | 12 days | 66 days |
| 2022 | 1,330 | 0 days | 7 days | 66 days |
| 2023 | 1,125 | 1 day | 23 days | 88 days |
| 2024 | 1,285 | 11 days | 45 days | 100 days |
| 2025 | 1,065 | 11 days | 42 days | 98 days |
| 2026* | 732 | 10 days | 44 days | 105 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Permit processing times in ZIP 60614: ZIP codes with similar overall timing
Permit processing times in ZIP 60614 has 6,952 issued records, a 3 days median, and a 28 days 75th-percentile wait in this release.
More Permit processing times in ZIP 60614 comparisons
The Permit processing times in ZIP 60614 cohort contains 6,952 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 1 dayRenovation & Alteration 33 daysEasy Permit Process 0 daysSigns 32 daysNew Construction 16 daysWrecking & Demolition 0 daysElevator Equipment 0 daysScaffolding 0 daysReinstated Permit 0 days