ZIP code × permit type

Easy Permit Process permits in ZIP 60614

The median easy permit process permit wait in ZIP 60614 was 0 days, based on 931 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked9312021–Sep. 15, 2026

The short answer

For Easy Permit Process permits in ZIP 60614, 931 issued permit records show a median processing time of 0 days; 75% were issued within 4 days and 90% within 14 days, covering January 2021 through September 15, 2026.

Typical wait0 daysmedian issued permit
Usually within4 days75% of records
Long-wait edge14 days90% of records
Evidence931issued permits

Not enough records for a year-over-year comparison.

Easy Permit Process permits in ZIP 60614: wait distribution

For Easy Permit Process permits in ZIP 60614, 931 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
62.5%
1–7 days
21.6%
8–30 days
11.9%
31–90 days
2.9%
91+ days
1.1%

Change over time

Easy Permit Process permits in ZIP 60614: annual permit timing

Easy Permit Process permits in ZIP 60614 has 3 publishable issue-year cohorts spanning 2021–2023, representing 926 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20213460 days2.8 days10 days
20223130 days4 days16 days
20232670 days5 days17 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Easy Permit Process permits in ZIP 60614: Easy Permit Process timing in comparable ZIP codes

Easy Permit Process permits in ZIP 60614 has 931 issued records, a 0 days median, and a 4 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 606030 days5 days93
ZIP 606050 days3.8 days230
ZIP 606060 days2 days247
ZIP 606070 days1 day522
ZIP 606080 days0 days756
ZIP 606090 days0 days660
ZIP 606100 days6 days521
ZIP 606120 days0 days539