Express Permit Program permits in ZIP 60614
The median express permit program permit wait in ZIP 60614 was 1 day, based on 2,934 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Express Permit Program permits in ZIP 60614, 2,934 issued permit records show a median processing time of 1 day; 75% were issued within 9 days and 90% within 30 days, covering January 2021 through September 15, 2026.
The median was 1 day faster than the previous 12 months.
Express Permit Program permits in ZIP 60614: wait distribution
For Express Permit Program permits in ZIP 60614, 2,934 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Express Permit Program permits in ZIP 60614: annual permit timing
Express Permit Program permits in ZIP 60614 has 6 publishable issue-year cohorts spanning 2021–2026, representing 2,934 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 459 | 0 days | 1 day | 17 days |
| 2022 | 406 | 0 days | 1 day | 14 days |
| 2023 | 350 | 0 days | 5 days | 70 days |
| 2024 | 706 | 2 days | 13 days | 37 days |
| 2025 | 589 | 5 days | 14 days | 35 days |
| 2026* | 424 | 3 days | 13 days | 27 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Express Permit Program permits in ZIP 60614: Express Permit Program timing in comparable ZIP codes
Express Permit Program permits in ZIP 60614 has 2,934 issued records, a 1 day median, and a 9 days 75th-percentile wait in this release.
More Express Permit Program permits in ZIP 60614 comparisons
The Express Permit Program permits in ZIP 60614 cohort contains 2,934 issued records; related links retain separate location and permit-category cohorts.