ZIP code × permit type

Express Permit Program permits in ZIP 60613

The median express permit program permit wait in ZIP 60613 was 1 day, based on 1,095 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked1,0952021–Sep. 15, 2026

The short answer

For Express Permit Program permits in ZIP 60613, 1,095 issued permit records show a median processing time of 1 day; 75% were issued within 8 days and 90% within 21 days, covering January 2021 through September 15, 2026.

Typical wait1 daymedian issued permit
Usually within8 days75% of records
Long-wait edge21 days90% of records
Evidence1,095issued permits

The median was 1 day faster than the previous 12 months.

Express Permit Program permits in ZIP 60613: wait distribution

For Express Permit Program permits in ZIP 60613, 1,095 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
40.5%
1–7 days
34.3%
8–30 days
18.9%
31–90 days
5.2%
91+ days
1.0%

Change over time

Express Permit Program permits in ZIP 60613: annual permit timing

Express Permit Program permits in ZIP 60613 has 6 publishable issue-year cohorts spanning 2021–2026, representing 1,095 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20211060 days3 days24 days
20221030 days3 days8.8 days
20231200 days4 days14 days
20242632 days12 days20 days
20252962 days10 days26 days
2026*2071 day8 days21 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Express Permit Program permits in ZIP 60613: Express Permit Program timing in comparable ZIP codes

Express Permit Program permits in ZIP 60613 has 1,095 issued records, a 1 day median, and a 8 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 606021 day9 days1,021
ZIP 606031 day9 days1,124
ZIP 606051 day10 days1,055
ZIP 606081 day7 days1,903
ZIP 606091 day7 days1,621
ZIP 606121 day7 days1,543
ZIP 606131 day8 days1,095
ZIP 606141 day9 days2,934