ZIP code × permit type
Express Permit Program permits in ZIP 60605
The median express permit program permit wait in ZIP 60605 was 1 day, based on 1,055 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Express Permit Program permits in ZIP 60605, 1,055 issued permit records show a median processing time of 1 day; 75% were issued within 10 days and 90% within 30 days, covering January 2021 through September 15, 2026.
The median was 1 day slower than the previous 12 months.
Express Permit Program permits in ZIP 60605: wait distribution
For Express Permit Program permits in ZIP 60605, 1,055 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Express Permit Program permits in ZIP 60605: annual permit timing
Express Permit Program permits in ZIP 60605 has 6 publishable issue-year cohorts spanning 2021–2026, representing 1,055 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 157 | 0 days | 5 days | 29 days |
| 2022 | 143 | 0 days | 27 days | 41 days |
| 2023 | 152 | 0 days | 7 days | 42 days |
| 2024 | 232 | 1 day | 9.2 days | 19 days |
| 2025 | 199 | 4 days | 7 days | 16 days |
| 2026* | 172 | 3 days | 13 days | 26 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Express Permit Program permits in ZIP 60605: Express Permit Program timing in comparable ZIP codes
Express Permit Program permits in ZIP 60605 has 1,055 issued records, a 1 day median, and a 10 days 75th-percentile wait in this release.
More Express Permit Program permits in ZIP 60605 comparisons
The Express Permit Program permits in ZIP 60605 cohort contains 1,055 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60605 permits ZIP reportExpress Permit Program citywide Type report