ZIP code × permit type
Renovation & Alteration permits in ZIP 60614
The median renovation & alteration permit wait in ZIP 60614 was 33 days, based on 1,363 issued records.
Records checked1,3632021–Sep. 15, 2026
The short answer
Typical wait33 daysmedian issued permit
Usually within84 days75% of records
Long-wait edge164 days90% of records
Evidence1,363issued permits
The median was 10 days slower than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 287 | 6 days | 50 days | 107 days |
| 2022 | 270 | 1 day | 51 days | 143 days |
| 2023 | 243 | 29 days | 90 days | 176 days |
| 2024 | 244 | 48 days | 96 days | 181 days |
| 2025 | 185 | 59 days | 108 days | 194 days |
| 2026* | 134 | 64 days | 112 days | 156 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context